As-Built, MEPF Coordination Drawings for USA Fedral Project
Project Overview
Client Profile
US Federal Government
Location
DC Naval Yard
Industry
Federal
Inputs
Project requirements
Deliverables
As-Built, MEPF Model Coordination, and Shop Drawing
Business Needs
- Comprehensive as-built documentation for Federal facility to serve as a baseline for design and construction.
- An efficient MEPF design system to integrate seamlessly with the operational infrastructure for DC, USA ensuring minimal disruption to ongoing activities.
- Develop construction-ready shop drawings to address the unique challenges posed by wetland conditions and ensure structural stability.
Challenges
DC Naval shipyard’s location in a wetland zone, reflecting environmental concern.
- Our primary concern was designing a robust foundation capable of supporting heavy naval infrastructure in these conditions.
- The naval facility’s role in supporting various operations demanded a well-coordinated MEPF system.
- Proximity to coastal areas required adherence to strict environmental regulations.
Project Samples
Our Solutions & Approach
Tejjy Inc. adopted a comprehensive and digitally innovative approach to address the project’s challenges and to deliver solutions adhering to the needs of the government. Our team-
- Created and delivered detailed shop drawings for a pile foundation system, ensuring the structure’s stability on unstable wetland soil.
- The design proposed minimized settlement risks and provided long-term durability for the naval yard’s heavy infrastructure.
- Developed a Level of Development (LOD) 350 BIM model for the MEPF systems using Autodesk Revit 2024 and Navisworks.
- Facilitated precise coordination among various disciplines with our 3D BIM model for government facilities and avoided clashes during construction.
- Worked closely with environmental consultants to incorporate measures that preserved the nearby marine ecosystem.
- Proactively addressed federal compliance requirements, ensuring the project adhered to all necessary guidelines related to coastal and wetland construction.
Business Impact
The coordinated MEPF design significantly improved facility operations by reducing waste, preventing delays, and ensuring seamless functionality. It enabled the naval yard to meet its operational goals without disruptions.
- The pile foundation system provided a robust base for the facility, addressing the challenges of wetland construction and ensuring long-term durability.
- This solution enhanced the overall structural integrity, enabling the naval yard to support its heavy engineering operations.
- By integrating environmental preservation measures, Tejjy successfully balanced structural needs with ecological responsibilities.
- The project set a precedent for achieving compliance without compromising on design or operational goals.